If any cable is discovered in the ground during work, then?
1
work should continue with caution
2
Work must be stopped immediately
3
Work must be stopped immediately and resumed only after official consent is obtained
Law explanation
If any cable is found in the ground during work, the work must be stopped immediately and continued only after official consent is obtained.
When bringing a machine into working condition or before moving it, in order to clear the work site of outsiders, the machine operator:
1
must give a sound signal
2
Must go to the work site and personally warn outsiders
3
must give the warning signal by hand
Law explanation
When bringing a mechanism into working position or before moving it, the operator must give a sound signal in order to clear the work area of unauthorised persons.
Before starting work, a stencil sign with an inscription must be placed at the work site?
1
"No entry"
2
about ongoing works
3
the machine operator's surname, first name and patronymic
Law explanation
Before work begins, a stencil sign with an inscription about the ongoing works must be placed at the work site.
May unauthorised persons be allowed on the excavator?
1
Possible together with the machine operator
2
possibly with the consent of the management
3
is not allowed
Law explanation
Unauthorised persons must not be allowed on an excavator.
When getting off an escalator, it is necessary:
1
Only that all levers be set to the neutral position
2
only switch off all the switches
3
performing all the actions listed in this ticket
Law explanation
When getting off the excavator, it is necessary to switch off all controls and put them in the neutral position.
May a machine be left in working condition?
1
possible for 15-20 minutes
2
yes
3
no
Law explanation
A machine must not be left in working condition.
May an excavator bucket be left in a loaded state raised off the ground?
1
the bucket must be lowered to the ground
2
possibly at a height of 1-1.5 metres from the ground
3
possibly at any height
Law explanation
If the excavator bucket is left in a loaded state, the bucket must be lowered to the ground.
During operation, at what distance must an outsider be kept away from the work site?
1
2 m
2
10 m
3
5 m
4
15 m
Law explanation
During operation, unauthorised persons must be kept at a distance of 15 metres from the work site.
At what distance must an outsider be kept away while repairs are in progress?
1
5 m
2
2 m
3
1.5 m
4
10 m
Law explanation
During repairs, unauthorised persons must be kept at a distance of 1.5 metres.
Work under high voltage is permitted if the distance between the highest point of the excavator and the high-voltage wires is not less than:
1
2 m
2
10 m
3
1.5 m
4
5 m
Law explanation
Working under high voltage is permitted if the distance between the highest point of the excavator and the power lines is not less than 2 metres.
The excavator must be equipped with:
1
None of the answers listed in this ticket is correct
2
only with a first-aid kit
3
with both a first-aid kit and fire-fighting equipment
4
only with fire-fighting equipment
Law explanation
An excavator must be equipped with both a first-aid kit and fire-fighting equipment.
Must a tractor driver-machine operator know the traffic rules?
Law explanation
A tractor driver-operator must know the traffic rules.
When must the required gear be engaged for a bulldozer to move on an inclined surface?
1
before starting to move on an inclined surface
2
When moving on an inclined surface
Law explanation
The gear required for a bulldozer to move on an inclined surface must be engaged before starting to move on the inclined surface.
When manoeuvring a bulldozer in a confined space or when climbing an uphill gradient, one must:
1
the crankshaft rotation speed should be reduced
2
the crankshaft rotation frequency should be increased
Law explanation
When manoeuvring a bulldozer in a confined space or climbing a slope, you should reduce the crankshaft speed.
Operation of a bulldozer is not permissible if:
1
Raising the blade and working the soil when the longitudinal slope exceeds 30°
2
raising the blade and working the soil when the longitudinal slope exceeds 15°
3
raising the blade and working the soil when the longitudinal inclination is more than 20°
Law explanation
Operating a bulldozer is not permitted if, when raising the blade and working the soil, the longitudinal slope exceeds 20°.
Operation of a bulldozer is not permissible if:
1
working on a slope with a parallel inclination of more than 16°
2
working on a slope with a parallel inclination of more than 24°
3
working on a slope with a parallel inclination of more than 20°
Law explanation
Operating a bulldozer is not permitted on a slope with a parallel inclination of more than 16°.
Is it permissible to make a turn with the bulldozer and the ripper tooth deeply buried?
Law explanation
Turning a bulldozer with the ripper tooth deeply embedded is not permitted.
A bulldozer can be transported:
1
Only by road transport
2
by any of the methods listed in this ticket
3
Only under its own power
4
only by rail transport
Law explanation
A bulldozer can be transported both under its own power and by road and rail transport.
Transporting a bulldozer over a short distance is recommended?
1
under its own power
2
by road transport
3
by rail transport
Law explanation
It is recommended to move a bulldozer over a short distance under its own power.
Transporting a bulldozer over a long distance is recommended?
1
only by rail transport
2
By any of the methods listed in this ticket
3
Only by road transport
Law explanation
For long-distance transportation of a bulldozer, both road and rail transport are recommended.
Practical part
Exam routes — exactly the way the examiner drives them
60 real exam routes across 10 cities, 793 km in total. Every turn and stop on the map, with voice guidance.
All routes on the map
GPS mode on the real road
Practice mode with adjustable speed
On the web and in the app
One-off payment, no auto-renewal — by card on the Bank of Georgia secure page.